The Dunn Place Subdivision & Townhomes includes three applications: Tentative Subdivision (S 1-23), Planned Development Amendment (PDA 1-23), and Three Mile Lane Review (TML 5-23)

 

Dunn Place Subdivision & Townhomes 

The applicant is requesting concurrent review and approval of three applications for the Dunn Place 21-Lot Subdivision and Townhouse Development.

Applicant:  Andrey Chernishov, HBH Consulting, on behalf of property owner Evergreen Court Townhomes LLC, c/o Jason Flores

Address:  235 NE Dunn Place
Map & Tax Lot:  R4422CD01700
Current Zone:  R-4 PD (Medium-High Density Residential with Planned Development Overlay)  

 

Applications:

The applicant submitted three applications:

S 1-23: Tentative Subdivision

PDA 1-23: Planned Development Amendment

TML 5-23: Three Mile Lane Design Overlay Review

Combined Application Material

 

Public Hearings:

Planning Commission:  December 7, 2023 at 6:30pm

Planning Commission:  January 4, 2024 at 6:30pm (continued from December 7, 2023)

Meeting Materials:

     Meeting Packet Materials for December 7, 2023 Planning Commission Hearing

     Additional Materials Submitted After November 30, 2023 Packet Materials Through December 7, 2023 Hearing:

          -December 7, 2023 Memo from Staff with the Following Attachments:
                    Attachment 1.  Written Public Testimony:
                   1a.  December 4, 2023 E-mail from Mike Full, with two attachments:
                        -November 28, 2023 Letter from William Orr, Oregon Registered Professional Geologist
                        -
October 20, 2004 Letter from William Orr, Oregon Registered Professional Geologist
                   1b.  December 6, 2023 E-Mail from Nanette Pirisky
                   1c.  December 6, 2023 E-Mail #1 from Joe Strunk with Attachments:
                         -
4 photos
                   1d.  December 6, 2023 E-Mail #2 from Joe Strunk with Attachment:
                          -December 6, 2023 Statement from Mike Full
                   1e.  December 6, 2023 E-Mail #3 from Joe Strunk with Attachment
                         -LIDAR Map Image
                   1f.  December 6, 2023 E-Mail from Dave and Barbara Tracy

                   Attachment 2.  December 7, 2023 Memo from Jason Bock, PE, GRI

                 Attachment 3.  December 7, 2023 E-Mail from Oregon Department of State Lands

          -Additional Materials Submitted by Andrey Chernishov, December 7, 2023
          -Additional Materials Submitted by Joe Strunk, December 7, 2023

     Additional Materials Submitted After December 7, 2023 Hearing:

        -Geotechnical Report - Addendum #1 from Strata Design, dated December 22, 2023

     Meeting Packet Materials for January 4, 2024 Planning Commission Continued Hearing

      Additional Materials Submitted After December 28, 2023 Packet Materials Through January 4, 2024 Hearing:

          -January 4, 2024 Staff Memo with the Following Attachments:
                 Attachment 1.  January 3, 2024 submittal from Andrey Chernishov, Applicant
             Attachment 2.  Four January 3, 2024 e-mails with attachments from Joe Strunk
             Attachment 3.  Letter from Dr. George Siegfried, submitted via e-mail by Mike Full on January 4, 2024
             Attachment 4.  January 4, 2024 e-mail from DLCD
             Attachment 5.  January 4, 2024 memo from Jason Bock, PE, GRI
         -January 4, 2024 Letter with attachments submitted by Joseph M. Strunk

Notice of Decision

Decision Document