Schedule:                             April 2020 – early 2025

Budget:                                $21.6 million

Funding source:                Wastewater Capital Fund 77

Engineer:                             Jacobs Engineering Group, Inc.

Prime contractor:             J.W. Fowler, Inc.

 

This project will increase the capacity of the solids treatment process at the City’s Water Reclamation Facility. The prime contractor, J.W. Fowler, will begin construction in late May 2023 and the project is expected to be completed in early 2025.

The treatment plant produces high quality class “A” biosolids that are applied to agricultural fields as a beneficial resource, adding moisture and nutrients to the fields during the summer land application season. The scope of work includes replacement of the existing solids treatment facilities with higher capacity, more efficient digestors, replacement of the existing odor control facility, improvements to increase solids storage capacity during winter months and upgrading instrumentation and control systems.

 

Contact Information

Manager:
Leland Koester
Phone: 503-434-7313
Fax: 503-434-7438

Project Manager:
Chip Ullstad
Phone: 541-754-7611

 

Click any thumbnail image to view a slideshow

Solids Treatment Capacity
Biosolids
Biosolids
Biosolids
Biosolids
Biosolids April
Biosolids April
May Progression
May Progression