Chandlers Addition Basin Sanitary Sewer Project
The Chandlers Addition Basin Sanitary Sewer Project will rehabilitate 5,300 lineal feet of aging sanitary sewer pipelines, ranging in size from 6 inch to 18 inch in diameter. The pipes will be rehabilitated with an assortment of techniques including open cut, pipe bursting and cured in place pipe (CIPP) lining.
*** PROJECT UPDATE*** The pipe work has been completed with a few punchlist items and final paving to be completed by June 30, 2025.
SCHEDULE:
FIELD INVESTIGATING AND SURVEY COMPLETED
ENGINEERING DESIGN COMPLETED
CONSTRUCTION PUNCHLIST AND FINAL PAVING TO BE COMPLETED BY JUNE 30, 2025