Chandlers Addition Basin Sanitary Sewer Project
The Chandlers Addition Basin Sanitary Sewer Project will rehabilitate 5,300 lineal feet of aging sanitary sewer pipelines, ranging in size from 6 inch to 18 inch in diameter. The pipes will be rehabilitated with an assortment of techniques including open cut, pipe bursting and cured in place pipe (CIPP) lining.
SCHEDULE:
FIELD INVESTIGATING AND SURVEY JANUARY – MARCH 2023
ENGINEERING DESIGN MARCH – NOVEMBER 2023
CONSTRUCTION JUNE – OCTOBER 2024